Regenerator Unit Repair Works on course

DSC03392Repair works at the regenerator unit of the RFCC is on course with the arrival of the refractory materials at the refinery.

TOR workers would within a period of 10 weeks extensively clean around cyclones in the Reactor, chisel and collect coke deposits, evacuate the catalyst from the Flue Gas Steam Generator (FGSG) and carry out hydro testing of the unit among others.

It is estimated that maintenance works would be completed by end of May and the processing plant will be back on stream by mid June. Works have however delayed since the refractory materials were air freighted